TS16949内审员考试试题 是非题:请指出下列问题是对还是错,对打 发布时间: 2012-01-03 20:38 点击:

TS16949内审员考试试题 是非题:请指出下列问题是对还是错,对打√,错打X(1X10=10分)
TS16949 auditor examination questions are: please point out the question whether it is right or wrong, the wrong play, X ( 1X10 = 10 points)
1. 管理层必须定期对管理体系进行评审。                          (  )
1 management must periodically review of management system. ( )
2. 如果公司在PPAP提交允许的日期之前仍不能达到接受准则,公司必须向顾客提交一份纠正措施计划和通常包含100%检验的控制计划。                 (  )
2 if the company in the PPAP to allow date still can not meet acceptance criteria, the company must submit to the customer a corrective action plan and usually contains 100% test control program. ( )
3.PFMEA分析的过程必须是过程流程图中描述的部分过程。          (   )
3.PFMEA analysis process must be a process flow diagram is described in part process. ( )
4.做测量系统分析的零件应产生于稳定的生产过程。                 (   )
4 do the measurement system analysis parts should be produced in stable production process. ( )
5.质量记录是一种特殊的文件,所以须按4.2.4的要求进行控制.        (  )
5 quality records are a special type of document, so it must be according to 4.2.4 requirements for control ( ).
6.组织必须对顾客的财产行验证,标识,维护等。                   (   )
6 organizations must on the customer property line authentication, identification, maintenance. ( )
7.必须对每个生产过程进行SPC的控制。.                          (   )
7 must each production process SPC control. ( ).
8.顾客要求我们按2级提交,所以我们内部制作的文件资料比按3级提交时少很多。                    (   )
8 customer demand us to submit 2 level, so our internal documents produced by the 3 submitted information than a lot less. ( )
9.必要时,审核员可以审核自已的工作 。                           (   )
9 if necessary, the auditor can check their own work. ( )
10.试生产后送样给客户就标志APQP的结束。                     (   )
10 trial production samples to customers on evacuation sign APQP end. ( )