当前位置: 网站首页 > 总站 > ISO9001认证 >
GB/T 50430-2007质量管理标准:10 工程项目施工质量管理 发布时间: 2011-10-25 17:17 点击:

 

GB/T 50430-2007质量管理标准:10  工程项目施工质量管理
GB / T 50430-2007: 10 quality management standard of construction project quality management
10.1  一般规定
10.1 general provisions
10.1.1    施工企业应建立并实施工程项目施工质量管理制度,对工程项目施工质量管理策划、施工设计、施工准备、施工质量和服务予以控制。
10.1.1 construction enterprise shall establish and implement the construction project quality management system, the construction project quality management planning, construction design, construction preparation, construction quality and service to control.
10.1.2    施工企业应对项目经理部的施工质量管理进行监督、指导、检查和考核。
10.1.2 construction enterprises to deal with project manager for the Department of the construction quality management of supervision, guidance, inspection and assessment.
10.2  策划
10.2 planning
10.2.1    施工企业项目经理部应负责工程项目施工质量管理。项目经理部的机构设置和人员配备应满足质量管理的需要。
10.2.1 construction enterprise manager department shall be responsible for the construction project quality management. Project manager for the Department of institutions and personnel shall meet the needs of quality management.
10.2.2    项目经理部应按规定接收设计文件,参加图纸会审和设计交底并超消费结果进行确认。
10.2.2 project manager shall receive the design documents, participate in the joint review of the drawings and design work and to confirm the results of consumption.
10.2.3    施工企业应按照规定的职责实施工程项目质量管理策划,包括:
10.2.3 construction enterprise should be in accordance with the provisions of the responsibility of implementing the project quality management planning, including:
1        质量目标和要求;
1 quality objectives and requirements;
2        质量管理组织和职责;
2 quality management organization and responsibilities;
3        施工管理依据的文件;
3 construction management on the basis of documents;
4        人员、技术、施工机具等资源的需求和配置;
4 staff, technology, construction equipment and other resources demand and allocation;
5        场地、道路、水电、消防、临时设施规划;
5 venues, road, water, fire, temporary facilities planning;
6        影响施工质量的因素分析及其控制措施;
Effect of 6 factors on the quality of construction and its control measures;
7        进度控制措施;
7 progress control measures;
8        施工质量检查、验收及其控制措施;
8 construction quality inspection, acceptance and its control measures;
9        突发事件的应急措施;
9 emergency measures;
10    对违规事件的报告和处理;
10 pairs of compasses incident reporting and handling;
11    应收集的信息及其传递要求;
11 collecting information and delivery requirements;
12    与工程建设有关方的沟通方式;
12 Construction and engineering of side communication mode;
13    施工管理应形成的记录;
13 construction management should form the record;
14    质量管理和技术措施;
14 quality management and technical measures;
15    施工企业质量管理的其他要求。
15 other requirements of the quality management in construction enterprises.
10.2.4    施工企业应将工程项目质量管理策划的结果形成文件并在实施前批准。策划的结果应按规定得到发包方或监理方的认可。
10.2.4 construction enterprise should be the quality management of engineering project planning results documented and approved before implementation. The planning results shall be the employer or supervisor approval.
10.2.5    施工企业应工程项目质量管理策划的结果实行动态管理,及时调整相关文件并监督实施。
10.2.5 construction enterprise engineering project quality management planning results in the implementation of dynamic management, timely adjustment of relevant documents and to supervise the implementation of.
10.3  施工设计
10.3 construction design
10.3.1    施工企业进行施工设计时,应明确职责,策划并实施施工设计的管理。施工企业应对其委托的施工设计活动进行控制。
10.3.1 construction enterprises construction design, should make clear duty, planning and implementation of construction design management. Construction enterprises should entrust the construction design activity control.