GB/T 50430-2007质量管理标准:8 建筑材料、构配件和设备管理 发布时间: 2011-10-25 17:15 点击:

 

GB/T 50430-2007质量管理标准:8  建筑材料、构配件和设备管理
GB / T 50430-2007 quality management standard: 8 building materials, components and equipment management
8.1  一般规定
8.1 general provisions
8.1.1  施工企业应根据施工需要建立并实施建筑材料、构配件和设备管理制度。
8.1.1 construction enterprise construction should be the establishment and implementation of building materials, components and equipment management system.
8.2  建筑材料、构配件和设备的采购
The 8.2 building materials, components and equipment procurement
8.2.1        施工企业应根据施工需要确定和配备项目所需的建筑材料、构配件和设备,并应按照管理制度的规定审批各类采购计划。计划未经批准不得用于采购。采购计划中应明确所采购产品的种类、规格、型号、数量、交付期、质量要求以及采购验证的具体安排。
8.2.1 construction enterprise construction should be identified and equipped with items necessary for building materials, components and equipment, and in accordance with the provisions of the approval of management system of procurement plan. Plan without approval shall not be used for purchasing. Procurement planning should be defined in the procurement of products, specifications, types, quantity, delivery time, quality and procurement verification arrangements.
8.2.2        施工企业应对供应方进行评价,合理选择建筑材料、构配件和设备的供应方。对供应方的评价内容应包括:
8.2.2 construction enterprises to deal with supplier evaluation, a reasonable choice of building materials, components and equipment suppliers. On the supply side of the evaluation should include:
1        经营资格和信誉;
1 qualification and reputation;
2        建筑材料、构配件和设备的质量;
The 2 building materials, components and equipment quality;
3        供货能力;
3 supply capacity;
4        建筑材料、构配件和设备的价格;
The 4 building materials, components and equipment price;
5        售后服务
5 service.
8.3.1            施工企业应在必要时对供应方进行再评价。
8.3.1 construction enterprise should be necessary to supplier re-evaluation.
8.3.2            对供应方的评价、选择和再评价的标准、方法、和职责应符合管理制度的规定,并保存相应的记录。
8.3.2 on the supply side of the evaluation, selection and evaluation standard, method, and responsibilities shall be in accordance with the management rules, and save the corresponding records.
8.3.3            施工企业应根据采购计划订立采购合同。
8.3.3 construction enterprise should according to purchasing plan signed purchase contract.
8.3  建筑材料、构配件和设备的验收
The 8.3 building materials, components and equipment acceptance
8.3.4            施工企业应对建筑材料、构配件和设备进行验收。必要时,应到供应方的现场进行验证。验收的过程、记录和标识应符合有关规定。未经验收的建筑材料、构配件和设备不得用于工程施工。
8.3.4 construction enterprises to deal with the building materials, components and equipment for acceptance. When necessary, should be to verify supplier site. The acceptance process, recording and marking shall be in conformity with the relevant provisions. Without the acceptance of building materials, components and equipment shall not be used for engineering construction.
8.3.5            施工企业应按照规定的职责、权限和方式对验收不合格的建筑材料、构配件和设备符合有关职业健康、安全与环保的要求。
8.3.5 construction enterprise should be in accordance with the provisions of the responsibility, authority and on the acceptance of unqualified building materials, components and fittings and equipment in accordance with the relevant occupation health, safety and environmental requirements.
8.4  建筑材料、构配件和设备的现场管理
The 8.4 building materials, components and equipment management of the site
8.4.1        施工企业应在管理制度中明确建筑材料、构配件和设备的现场管理要求。
8.4.1 construction enterprise should be in the management system of clear building materials, components and equipment to the site management.
8.4.2        施工企业应对建筑材料、构配件和设备进行贮存、保管和标识,并按照规定进行检查,发现问题及时处理。
8.4.2 construction enterprises to deal with the building materials, components and equipment storage, preservation and identification, and in accordance with the provisions of inspection, found problems in a timely manner.