当前位置: 网站首页 > 总站 > ISO9001认证 >
建筑业ISO9000认证中每项工程符合《质量计划》的定义 发布时间: 2012-01-15 02:00 点击:

建筑业ISO9000认证中每项工程符合《质量计划》的定义
Construction of ISO9000 authentication in every project in line with" quality project" definition
   《ISO8402 质量管理和质量保证术语》质量计划的定义为:
" The ISO 8402 quality management and quality assurance." quality plan is defined as:
   “针对特定的产品、项目或合同,规定专门的质量措施、资源和活动顺序的文件”。
" For a specific product, project or contract, provisions of special quality measures, resources and activities sequence file".
   由质量计划的定义我们体会到:
The quality plan definition we experience:
   1.质量计划的对象是特定的产品、项目或合同,建筑产品是单项大型的产品,按业主的要求进行设计,施工单位按设计图进行施工,每项工程都按国际惯例,大都实行项目经理部制,且事先订有合同。
1 quality plan is the object of a specific product, project or contract, construction products is a single large products, according to the owners of the requirements for the design, construction units according to the design and construction, each project according to international practice, most project manager department, and prior to a contract.
因为,每一个工程既是特定的产品、项目,又订有合同。因此,质量计划对建筑工程项目更具有针对性。
Because, every project is a specific product, project, and a contract. Therefore, the quality plan for construction project is more targeted.
   2.质量计划是“规定专门的质量措施、资源和活动顺序的文件”,也就是说,在质量计划里要明确规定为满足要求所采取的质量措施、所需资源以及必须进行的一系列质量活动,而且要形成书面文件。
2 quality plan is" specified quality measures, resources and activities sequence file", that is to say, in the quality plan must be defined in order to meet the requirement to quality measures, required resources and must undertake a series of quality activities, but also to form a written document.
   3.“质量计划通常参照质量手册适用于特定情况的有关部分”,说明它应与手册规定的要求相一致。
3" quality plan usually refer to the quality manual is suitable for a particular situation, the relevant part of the" that it should be consistent with manual requirements.
建设工程项目的质量要求,正是质量计划要求的特定情况。
Construction project quality requirements, it is quality program requirement for specific situations.
   因此,除一个建筑公司应制定一整套覆盖全公司的质量体系外,各工程项目应按公司的质量体系文件,引用到其工程项目,并对其工程项目的具体情况细化建立该工程项目的《工程项目质量计划》。
Therefore, in addition to a construction company should develop a set of covering the whole of the company's quality system, the project should be according to the company's quality system documents, reference to the project, and the concrete engineering project refinement to establish the project" project quality plans".